To facilitate time bound approvals, time limits for disposal of application of various services by the concerned Departments have been specified in the Odisha Industries Facilitation Rules, 2015.
As per the rules, every concerned Department or Authority is expected to issue the required clearances after processing the application within the pre-defined time limit. In case of failure to issue the required clearances within the specified time limit, such clearances shall be deemed to have been issued and the entrepreneurs may proceed with the implementation of the projects.
The timelines for various approvals are mentioned in the table below:
Sl# | Service | Time Limit (Working Days) |
---|---|---|
DISCOMs | ||
1 | Time taken from request for connection to release of connection where infrastructure is available | 15 |
2 | Time taken from request for connection to release of connection where infrastructure is not available | 30 |
Odisha State Pollution Control Board | ||
3 | Consent to Establish | |
a | ‘A’ Category after obtaining environmental clearance | 60 |
b | ‘B’ Category after obtaining environmental clearance | 45 |
c | ‘C’ Category | 30 |
4 | Permission under Hazardous Waste (Handling & Management) Rules | 30 |
5. | Consent to Operate | |
a | ‘A’ Category after obtaining environmental clearance | 60 |
b | ‘B’ Category after obtaining environmental clearance | 45 |
c | ‘C’ Category | 30 |
Directorate of Factories and Boilers | ||
6. | Approval of Factory Plan for Non-Hazardous factories | 30 |
7. | Approval of Factory Plan for Hazardous factories | 60 |
8. | Approval of Factory Plan for Major Accident Hazard (MAH) factories | 90 |
9. | Registration and Licensing of Factories | 30 |
10. | Renewal/Amendment/Transfer of factory license | 30 |
11. | Issue of duplicate license | 30 |
12. | Inspection of Boilers & issue of provisional orders to operate boilers | 15 |
13. | Approval of repair order of Boilers | 15 |
14. | Steam pipeline drawing approval | 30 |
15. | Registration of Boilers | 30 |
16. | Endorsement of Certificates of Boiler Operation Engineers, Boiler Attendants and Welders issued by other States | 15 |
17. | Revalidation of Welders’ certificates | 15 |
Labour Commissioner | ||
18. | Registration under Odisha Shop and Commercial Establishment Act,1956 | 15 |
19. | Renewal of Registration under Odisha Shop and Commercial Establishment Act,1956 | 15 |
20. | Contract Labour(R & A)Act,1970 i)Registration (one time) ii)Licence iii)Renewal (annual) | 15 |
21. | Industrial Employment Standing Order Act, 1946 | 45 |
Urban Development Authorities(UDA) / Municipalities | ||
22. | Building Plan Approval | 60 |
23. | Issuance of Occupancy Certificate (Applicable to Bhubaneswar Development Authority and other Development Authorities & ULBs | 30 |
24. | Trade License | 15 |
25. | Water Connection | 45 |
26. | Conversion of Land Use under master plan | 60 |
Commercial Taxes | ||
27. | Registration under VAT Act | 1 |
28. | Registration under CST Act | 1 |
29. | Registration for Profession Tax | 1 |
Industries Department | ||
30. | Sanction of incentives under IPR 2015 | 30 |
IDCO | ||
Decision on Land Allotment within IDCO Estates outside BMC Area | ||
31. | Allotment Letter after receipt of recommendation letter from Single Window Authority | 30 |
32. | Execution of Lease Agreement subject to compliance of Terms and conditions of allotment | 15 |
33. | Issue of Possession Certificate | 15 |
Decision on Land Allotment within IDCO Estates within BMC Area | ||
34. | Allotment Letter after receipt of recommendation from HLCC | 30 |
35. | Execution of Lease Agreement subject to compliance of T & C | 15 |
36. | Issue of Possession Certificate | 15 |
MSME Department | ||
37. | Approval of EM-1 | 1 |
38. | Approval of EM-2 | 2 |
39. | Sanction of Interest Subsidy, Capital Investment Subsidy and VAT Reimbursement | 30 |
Directorate of Fire | ||
40. | No Objection Certificate | 30 |
Other Services | ||
41. | Conversion of land use in all other areas (except ULBs) | 60 |
42. | License under Drug and Cosmetics Act | 30 |
43 | Timelines for resolution of investor grievances | 45 |